| When | Item | Notes |
|---|---|---|
| W1–W3 · Apr 27 – May 17 | Finishes selection sprints + sub pricing conversations | Hodge + subs locked into firm prices. Coordinate with CMS DD outputs. P500 logs every quote. |
| W1–W4 | Appraisal in flight | Already kicked off. Keep appraiser supplied with comps + pro forma updates. |
| W3 · May 11 – May 17 | Finishes locked → final budget package | Locked GMP into P500. Single biggest schedule risk on the page. |
| W4–W5 | Loan package submitted to bank | Locked budget + fresh appraisal + leasing pipeline traction = bank package. |
| W6–W8 | Loan official approval / close | Conditional approval likely earlier; formal close gated on appraisal + GMP. |
| W9+ · ongoing | Construction execution + draws via P500 | Vertical construction Jun–Sep, then interior build-out. |
| When | Item | Notes |
|---|---|---|
| W1–W4 | DD wrap-up | Cafe + wellness club finishes, equipment, layout. Specs ready for sub pricing. |
| W5–W12 | CDs · pricing · VE | Construction docs out. VE pass to hold the locked GMP. |
| W13–W24+ | Procurement (cafe FF&E + wellness equipment) | Long-lead items first. Coordinate with vertical construction. |
| Open | Residential interiors (44 units) — designer/scope TBD | Not in CMS scope. Decide owner: separate ID, in-house, or template kit. |
| When | Item | Notes |
|---|---|---|
| W1–W8 | Leasing pipeline | LOS-597 self-touring · LOS-603 application & screening · LOS-537 waitlist admin · source tracking. |
| W9–W17 | Reservations + deposits + pre-leasing infrastructure | Stripe deposit handling. Tour-to-application funnel instrumented. |
| W18–W22 | Public launch (Sep) | Marketing site live, leasing pipeline open. Pre-leasing campaign starts. |
| When | Item | Pri | Notes |
|---|---|---|---|
| W1–W3 | Polish & deploy | P0 | Railway deploy + custom domain · AI personality (gender-aware) · post-processing · outbound queue · scheduler · iMessage features · Oura sync. |
| W4–W6 | Stripe storefront + Bundle of All | P0 | Custom Stripe + Supabase + Next.js. $49/mo coaching sub + auto-ship resold Thorne. Order management. |
| W9 · ~Jun 22 | SOFT LAUNCH · private link · 10–25 paying users | Revenue | Coaching subs + supps only. No Rx, no labs yet. First dollars. |
| W7–W12 | Partner integrations begin | P1 | CareValidate, Quest white-label, PerfectRx. BAAs → sandboxes → real testing. |
| W10–W13 | AI foundations | P1 | HBC-102 product catalog AI context · HBC-103 DB-backed AI config · HBC-104 knowledge base · SMS commerce v1 (only-if-asked). |
| W14–W17 | Founding members beta · 50–100 users | P0 | Admin dashboard · photo food logging · gender-segmented coaching. |
| W18–W21 | Agent architecture | P0 | HBC-105 router → specialists · HBC-106 memory · HBC-109 auto-judge · HBC-107 staff takeover. |
| W22–W24 | Public launch window | Public | Lab results AI analysis · proactive commerce triggers · abandoned cart · digital product delivery. |
| W22–W24+ | Private label kickoff (not delivery) | P2 | Pick manufacturer · NDA · 2–3 hero SKUs in formulation. Shipping in 2027. |
| Q4 2026 / 2027 | Truemed · dynamic pricing engine · multi-coach | P2 | Deferred. Add after public launch is stable. |
| When | Item | Notes |
|---|---|---|
| W1–W8 | Photography · content · floor plans · SEO schema | ApartmentComplex schema markup. Content blog (no competitor does this). |
| W9–W17 | Virtual tours · social proof · reservation system | 3D/video walkthroughs. Testimonials, press, team credentials. |
| W18+ | Live for LobbyOS public launch (Sep) | Hard date pegged to LobbyOS launch. |
One product, one codebase target.
Soft launch ~W9. National public launch Wks 22–24.
Launch with Thorne et al. Private label is a 2027 program.
No Shopify. Supabase + Next.js + Stripe Billing.
No app store.
No proactive product pushing.
Vasari-branded lab requisitions.
Rx + supps + OTC in one shipment.
Dynamic pricing scales with labs/Rx/supps.