Vasari · Master Plan

Right now — this week

Pulled from Nanoclaw (Vasari PM). Top of the page on purpose — if it's not here, it's not happening this week.

This week (July 2 – 8, 2026)

  • 🔴 Borge metal panels — COLOR DUE TODAY (Jul 2): 14-day price guarantee expires. Select color now or reprice from scratch.
  • 🔴 Brick — go to King's Material NOW: Brad Bunn. Site visit was Jun 9. Still no written pricing or order. 3+ weeks overdue. Blocking facade budget.
  • 🔴 West Bank loan docs — overdue: Expected Jun 26. Matt Evans (title) resolving ownership record. Follow up with Jim Conard.
  • 🔴 Cabinet vendor — DECIDE THIS WEEK: Overdue from Jun 25 OAC. Corridor + Heartland + Highland quoted. Pick one.
  • 🔴 Elevator finishes — reply to Nolan Sullivan (Slingshot): Overdue since Jun 22. Masons start ~4–6 wks; approved shops needed to set embeds.
  • 🔴 Platform HS FF&E — send style/finish refs to Ardy Akad: 13+ days overdue (due Jun 19). 20–25 week lead time — every day slips spring 2027 install.
  • 🟡 Budget review today (Jul 2): Meeting with Jesse — financials, vacancy modeling, pro forma review.
  • 🟡 Door property tech — intro call Jul 2: Exploring access control + building OS integration for Vasari. Competing with Butterfly.
  • 🟡 IKEA Interior Design touchbase — Jul 1 happened: Follow up on next steps from that call.
  • 🟡 Leasing office electrician — due Jul 10: Book now to rewire lighting (overheads out, spotlights isolated). Opens Aug 1.
  • 🟡 WaterRower — send equipment list to Trevor Harper: 44 in-unit + gym + leasing office. Trevor needs list to start quote.
  • 🟡 Window shades — Roby to pick bid: Justin Wainwright (Hodge) coordinating. Choose Bid 2, 3, or 4 (manual vs. motorized).
  • 🟡 MPL shower confirmations: Justin asked Jun 26 — confirm 72" showers have no glass door (just 40" fixed panel). Reply needed.
  • 🟡 Hodge equity paperwork — prepare for signing: Andy, Mike Hodge, Kevin Digmann, Weston Hodge, Shane Morelock. $150K deferred from GC fee.
  • 🟡 Mezzanine drain + supply patch: Schedule Mulford to patch before floors go in.
  • 🟡 L1 restrooms — city ruling still pending: Jacob at city must rule single-user vs. gendered ADA pairs. Blocking L1 floor-plan finalization.
  • 🟡 Café CAD layout — still awaiting Jack (SPX): Needed by Janine (Chuck Marie) for DD. No date confirmed. Blocking design development.

Completed since last update (Jun 24 – Jul 2)

  • ✅ OAC meeting held — Jun 25: Construction coordination. Budget, siding progress, mass excavation underway.
  • ✅ Brand homepage R1 review — Jun 26, 1 PM: Call with Rachael Gibilterra. Figma R1 reviewed (Desktop + Mobile).
  • ✅ Elevator finishes call — Jun 26: Call with Nolan Sullivan re: alternate finishes. Still awaiting Roby's reply decision.
  • ✅ MPL Teams meeting — Jun 26: Kevin Kurschner + Justin Wainwright (Hodge) reviewed shower surround options.
  • ✅ IKEA Interior Design touchbase — Jul 1: Meeting completed. Follow-up actions TBD.
  • ✅ Mass excavation underway — started Jun 22: ~15 working days. Site active.
  • ✅ Mulford selected as plumber — Jun 20: Replaces Kohler. Finishes locked for first floor. SCS submittal unblocked.
  • ✅ Nail fin windows approved-as-noted — Jun 20: Caitlyn Reischauer (Slingshot) approved Submittal 08 5413-1.0. Ball in Hodge's court.
  • ✅ Roller shades decided — Jun 20: $68K refined bid + $8.8K manual = $76.8K total.
  • ✅ West Bank B.O. forms returned — Jun 19: Signed forms back to Jim Conard.
  • ✅ Drew (8VC) investment closed — Jun 19: $100K. Total raised: $5.5M. Appraisal: $21.7M. Financing: 5.5% / 5 yr.
  • ✅ Andy Hodge equity structure confirmed — Jun 18: Hodge deferring $150K from GC fee. $50K cash payment to follow.
  • ✅ SPX combined proposal received — Jun 23: Jack Tucker sent revised gym + café/locker room/shower ID scope.
  • ✅ Flooring awarded — Randy's: Interface 4.5mm LVP, $173K.
  • ✅ Gypcrete decided: Gypcrete HP 1" + Acousti-Mat 3/8" — $82,400 total.
  • ✅ WFHTC Application #664575 submitted — Jun 10: Up to $922,758 potential. Awaiting IEDA review.

Overdue / blocked

  • 🔴 Brick — King's Material (Brad Bunn): Site visit Jun 9. No pricing, no order. 3+ weeks overdue.
  • 🔴 Borge panel color: Price window expires TODAY (Jul 2). Select color immediately.
  • 🔴 West Bank loan docs: Expected Jun 26. Still pending Matt Evans (title).
  • 🔴 Cabinet vendor: Decision overdue from Jun 25 OAC. Corridor + Heartland + Highland quoted.
  • 🔴 Elevator finishes — Nolan Sullivan: Overdue Jun 22. Masons in ~4–6 wks; shops needed.
  • 🔴 Platform HS (Ardy Akad): Style refs overdue since Jun 19. 20–25 wk lead time.
  • 🔴 SPX gym — follow up with Jack: Proposal received; signed? Bailey kickoff status unknown.
  • 🔴 FF&E Multifamily Supply — Dan Ernest: Pricing due ~Jun 13. 3 weeks no response.
  • 🔴 Windows — Lite vs. Pella: Last contact May 22. 6+ weeks stale.
  • 🔴 Kitchen appliances vendor: Midea out. No replacement selected.
  • 🔴 L1 restrooms — city ruling: Jacob at city — ruling overdue. Blocking L1 floor plan.

Open items

  • Leasing Office: Opens Aug 1. Electrician booking due now (before Jul 10).
  • WaterRower (Trevor Harper): 44 in-unit + 8,600 sf gym + leasing office showcase. Send equipment list to start quote.
  • MPL showers: Confirm 72" units = no glass door, 40" fixed panel (Justin Wainwright asked Jun 26).
  • Window shades: Select from Bid 2/3/4 — Jon Farace (Commercial Shading). Justin Wainwright coordinating.
  • Hodge equity docs: Prep for Andy, Mike Hodge, Kevin Digmann, Weston Hodge, Shane Morelock.
  • Mezzanine drain: Schedule Mulford to patch before floors go in.
  • FF&E sourcing: Platform HS (Ardy, Egypt) blocked on style refs. Article (Tanis Glass) proposal pending. Richelieu + Wilsonart pricing needed.
  • Countertops: Richelieu (Wilsonart Thinscape) + Cosentino both in play.
  • Roofing: InvisiWeld confirmed. West Branch pricing pavers + pedestals ($212K + $100K).
  • Iowa athletes: Arrange building tour with Tate, Sage, Trevin via Kyle Denning (Iowa).
  • Iowa City brand launch: Wellness event Aug 22, 7:30am–2pm, downtown. Planning in progress.

Roby's open items

  • 🔴 Select Borge panel color — TODAY (Jul 2, price window closes)
  • 🔴 Visit King's Material — brick selection + order (Brad Bunn)
  • 🔴 Pick cabinet vendor — Corridor / Heartland / Highland (overdue Jun 25)
  • 🔴 Reply to Nolan Sullivan re: elevator finishes
  • 🔴 Send style refs to Ardy Akad (Platform HS) — overdue Jun 19
  • Confirm: 72" showers = no glass door, 40" fixed panel (Justin Wainwright asked Jun 26)
  • Select window shades bid (Bid 2/3/4) — Jon Farace
  • Send WaterRower equipment list to Trevor Harper
  • Book leasing office electrician (due before Jul 10)
  • Follow up on West Bank loan docs (Jim Conard)
  • Kitchen appliances — select replacement vendor for Midea
  • Window vendor — Lite vs. Pella (6 weeks stale)
  • Iowa athletes — arrange tour (Kyle Denning)
Last updated by Nano · July 2, 2026 · 11:30 AM CT
M
Apr 28
T
29
W
30
T
May 1
F
2
S
3
S
4
M
5
T
6
W
7
T
8
F
9
S
10
S
11
Construction
VE sub meetings
Appraisal in flight
CMS Design
DD weekly check-ins
LobbyOS
Self-touring + screening sprints
Vasari Health
Polish & deploy (P0)
Marketing
Photography brief

Construction & Financing · this 2 weeks

  • Finishes selection sprints — book the working sessions; no "we'll come back to it."
  • Sub pricing conversations on each locked finish — Hodge coordinates.
  • Keep appraiser fed: comps, leasing pipeline traction, pro forma.

CMS · this 2 weeks

  • Cafe DD wrap-up — finishes, equipment, layout signed off.
  • Wellness Club DD wrap-up — Pilates, sauna, plunge, IV/NAD+ recovery program.
  • Active Residential interiors (44 units) — Roby managing. VE in progress: reviewing all vendor quotes line by line.

LobbyOS · this 2 weeks

  • LOS-597 self-touring — flow + access integration with Swiftlane.
  • LOS-603 application & screening — apply form + screening provider.
  • LOS-537 waitlist admin — auto-promotion logic.

Vasari Health · this 2 weeks

  • Railway production deploy + custom domain + SSL + health checks.
  • AI personality system: tone, name, gender-aware from day one.
  • Message post-processing: multi-bubble splits, content filters.
  • Oura OAuth complete + daily sync cron.
  • Outbound message queue + iMessage typing/read receipts/tapbacks.

Marketing Site · this 2 weeks

  • Photography brief + shoot scheduling.
  • Content brief: blog topic ladder + ApartmentComplex schema plan.

Decisions due in this 2 weeks

  • Owner / scope for residential FF&E (CMS is cafe + wellness only).
  • Photography vendor + shoot date.
  • Hard finish-lock cutoff date (target: end of W3, May 17).

Critical milestones · next 4 weeks

  • May 17: Finishes locked. P500 reflects locked GMP.
  • May 24: Appraisal completed. Loan package out the door.
  • May 17: Vasari Health polish complete — storefront next.

Don't get pulled into

  • CareValidate / Quest / PerfectRx integration code (contracts can start; code starts W7+).
  • Agent architecture, memory extraction, photo food (Phase 3 — W14+).
  • Private label sourcing.
  • Public marketing launch.
Apr
May
Jun
Jul
Aug
Sep
Oct
W1
W2
W3
W4
W5
W6
W7
W8
W9
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
W21
W22
W23
W24
Construction & Fin.
VE + finishes lock
Loan package → close
Construction execution
CMS Design
DD wrap-up
CDs · VE · procurement
LobbyOS
Leasing pipeline
Reservations → public launch (Sep)
Vasari Health
Polish → Soft launch (W9)
Integrations + AI foundations
Public launch
Marketing Site
Photography · content · SEO
Build-out → live (Sep)
Construction & Fin. CMS Design LobbyOS Vasari Health Marketing Planned (not locked)

1 · Construction & Financing

Top priority · gates everything else
WhenItemNotes
W1–W3 · Apr 27 – May 17Finishes selection sprints + sub pricing conversationsHodge + subs locked into firm prices. Coordinate with CMS DD outputs. P500 logs every quote.
W1–W4Appraisal in flightAlready kicked off. Keep appraiser supplied with comps + pro forma updates.
W3 · May 11 – May 17Finishes locked → final budget packageLocked GMP into P500. Single biggest schedule risk on the page.
W4–W5Loan package submitted to bankLocked budget + fresh appraisal + leasing pipeline traction = bank package.
W6–W8Loan official approval / closeConditional approval likely earlier; formal close gated on appraisal + GMP.
W9+ · ongoingConstruction execution + draws via P500Vertical construction Jun–Sep, then interior build-out.

2 · CMS · Cafe + Wellness Club

Hospitality scope only — not residential units
WhenItemNotes
W1–W4DD wrap-upCafe + wellness club finishes, equipment, layout. Specs ready for sub pricing.
W5–W12CDs · pricing · VEConstruction docs out. VE pass to hold the locked GMP.
W13–W24+Procurement (cafe FF&E + wellness equipment)Long-lead items first. Coordinate with vertical construction.
ActiveResidential interiors (44 units) — Roby managingVE in progress — Roby reviewing all vendor quotes line by line across the full project.

3 · LobbyOS

Public launch Sep 2026
WhenItemNotes
W1–W8Leasing pipelineLOS-597 self-touring · LOS-603 application & screening · LOS-537 waitlist admin · source tracking.
W9–W17Reservations + deposits + pre-leasing infrastructureStripe deposit handling. Tour-to-application funnel instrumented.
W18–W22Public launch (Sep)Marketing site live, leasing pipeline open. Pre-leasing campaign starts.

4 · Vasari Health

Hot Body Coach (HBC) is the AI coach within Vasari Health · Soft launch ~W9 · public launch Wks 22–24
WhenItemPriNotes
W1–W3Polish & deployP0Railway deploy + custom domain · AI personality (gender-aware) · post-processing · outbound queue · scheduler · iMessage features · Oura sync.
W4–W6Stripe storefront + Bundle of AllP0Custom Stripe + Supabase + Next.js. $49/mo coaching sub + auto-ship resold Thorne. Order management.
W9 · ~Jun 22SOFT LAUNCH · private link · 10–25 paying usersRevenueCoaching subs + supps only. No Rx, no labs yet. First dollars.
W7–W12Partner integrations beginP1CareValidate, Quest white-label, PerfectRx. BAAs → sandboxes → real testing.
W10–W13AI foundationsP1HBC-102 product catalog AI context · HBC-103 DB-backed AI config · HBC-104 knowledge base · SMS commerce v1 (only-if-asked).
W14–W17Founding members beta · 50–100 usersP0Admin dashboard · photo food logging · gender-segmented coaching.
W18–W21Agent architectureP0HBC-105 router → specialists · HBC-106 memory · HBC-109 auto-judge · HBC-107 staff takeover.
W22–W24Public launch windowPublicLab results AI analysis · proactive commerce triggers · abandoned cart · digital product delivery.
W22–W24+Private label kickoff (not delivery)P2Pick manufacturer · NDA · 2–3 hero SKUs in formulation. Shipping in 2027.
Q4 2026 / 2027Truemed · dynamic pricing engine · multi-coachP2Deferred. Add after public launch is stable.

5 · Marketing Site (the building)

Live by LobbyOS Sep launch
WhenItemNotes
W1–W8Photography · content · floor plans · SEO schemaApartmentComplex schema markup. Content blog (no competitor does this).
W9–W17Virtual tours · social proof · reservation system3D/video walkthroughs. Testimonials, press, team credentials.
W18+Live for LobbyOS public launch (Sep)Hard date pegged to LobbyOS launch.

Top risks (in order)

  1. Finishes don't lock in 3 weeks. Cascades into delayed budget lock, delayed loan close, delayed everything.
  2. CareValidate / Quest / PerfectRx onboarding slips. Multi-party paperwork. Kick off contracts in W1, not W7.
  3. Roby attention split. Construction + CMS + LobbyOS + Vasari Health all compete.
  4. Dual launch in Sep/Oct. LobbyOS + Vasari Health within 4–6 weeks. Stagger or pick.
  5. Soft launch users churn before partner stack is live. Frame as "founding members."
  6. Residential interior owner unassigned. 44 units don't furnish themselves.
Furniture, Fixtures & Equipment tracker — residential units, wellness club, and café. Updated manually by Nanoclaw.
Locked Selection finalized Ordered PO issued Quoting Bids in progress TBD Not started At risk Blocking or overdue

Residential Units (44 units)

Owner-provided scope — Roby managing
CategoryStatusVendor / ProductNotes
Flooring (LVP)QuotingRandy's Carpets · Sobaskis4–4.5mm glue-down. Two competing bids in progress. Target ~$220–250K installed.
Shower basesQuotingAquatic (preferred) · Onyx (fallback)Pre-fab pans replacing tile showers — saves ~$27K. Tile shower walls also eliminated (~$160K saves).
ToiletsLockedProFlow / MoenSwitched from Kohler. Final pricing TBD from Hodge.
FaucetsLockedMoenSwitched from Kohler. Final pricing TBD.
Cabinets / caseworkQuotingHeartland · KBD · Corridor · IdealHeartland quote expected ~May 4. Ideal quote received: $5,949.70 (1BR L-shape, Standford Vanguard Oak). Apples-to-apples comparison pending.
Interior doorsLockedHollow-core white paintedStandard height. Significant savings vs. white oak 8ft spec. Final pricing from Hodge.
Door hardwareLockedSchlage leversStandard passage hardware. Allowance TBD for upgrade option. Roby researching cost-effective options.
Unit entry (smart lock)QuotingWal electronic strikePricing from Wal pending. Frame upcharge ~$400/door with electric strike (88 frames = ~$35K impact).
Kitchen appliancesAt riskVendor TBDMidea eliminated (can't do volume pricing). Need alternate vendor. Was $250K in Roby's scope (replacing $453K Hodge appliance allowance).
ThermostatsLockedEcobeeConfirmed. Integrates with LobbyOS IoT VLAN.
Lighting fixturesTBDNot yet spec'd. Part of Level 1 Design scope with Chuck Marie.
Window coveringsTBDNot yet spec'd.
Water filtrationTBDWhole-building filtration being explored as marketing feature. No charge or allowance model TBD.
Air quality (per unit)TBD~$30/unit add-on being explored as marketing feature for athlete tenants.
Floor outletsTBDOpen item — Roby to source.

Wellness Club

CMS (Chuck Marie) procurement scope · target Mar 31, 2027
CategoryStatusVendor / ProductNotes
Cardio equipmentLockedAtlantisSelected over Technogym — saves $150K+. SPX coordinating (Chloe / Sean).
Strength equipmentLockedHammer StrengthSelected over Technogym. SPX coordinating.
SaunaLockedSingle communal premium~$110K budget. Vendor not yet selected. Communal model decided (no per-unit saunas).
Cold plungeLockedCommercialConcept locked. Vendor TBD.
Pilates / LagreeTBDVendor TBD. Part of CMS DD wrap-up.
IV / NAD+ recoveryTBDProgram concept locked. Equipment and vendor TBD — part of CMS DD wrap-up.
Flooring (gym)TBDSpec TBD from Chuck Marie / Olson Kundig DD phase. Amber Fulgham (OKA) coordinating.
Lighting (gym + spa)TBDPart of CMS DD scope.

Café

Concept: Foxtrot meets Blank Street — minimal, labor-light, grab-and-go
CategoryStatusVendor / ProductNotes
Equipment layout (CAD)At riskJack (L1 kitchen specialist)Janine needs CAD layout within ~2 weeks for DD phase. Jack to provide. Blocking CMS DD.
Espresso / coffeeTBDLabor-light format — likely auto or semi-auto machine. Vendor TBD after layout locked.
Refrigeration / grab-and-go casesTBDLinear bar counter format. Equipment TBD after CAD layout.
POS systemTBDWill integrate with LobbyOS / Vasari OpCo operations.
Furniture / seatingTBDFirst-look from Chuck Marie early June.
Last updated by Nanoclaw · May 5, 2026 · 7:40 PM
Recent Vasari meetings — pulled from Granola. Last synced Apr 30, 2026.
Construction Project 500 Budget Meeting Apr 23, 2026 · 10:00 AM
Roby · Andy Hodge (Hodge Construction) · Jake Gorvin · Justin Wainwright
  • Andy's full bid: $16,276,001 — $1.36M over proforma baseline West Bank sees ($14,916,067)
  • VE options identified: flooring ($750K), millwork ($170K), plumbing ($175K mid), casework ($87.5K mid), ACM TBD
  • Appliances ($453K) removed from Andy's scope — Roby providing Midea direct ($250K)
  • After VE midpoints applied, Andy's adjusted scope is ~$276K under proforma baseline
  • MidAmerican Energy ($50K) confirmed as owner-provided item
  • Justin coordinating VE sub meetings this week (MEP, millwork, tile)
  • Elevator upgrade decision pending: $20K for 150→300 fpm speed upgrade (affects precast)
CMS Design Vasari · CMS Level 1 Interior Design · Weekly Check-In Apr 23, 2026 · 12:00 PM
Roby · Nolan Sullivan (Slingshot) · Steve Miller (Slingshot) · Janine MacKenzie (Chuck Marie) · Patrick Di Rito (Chuck Marie) · Nate Kaeding · Jesse · Sean (SPX) · Michael Paraszczak (Olson Kundig)
  • Gym/fitness floor plan options reviewed — page 1 of 260409-pfp_Vasari-plan options-v2.pdf is current working layout
  • Amber Fulgham (Olson Kundig associate) requested fitness plans — Janine sent PDF Apr 28
  • Sean (SPX) has updated equipment layouts not yet shared with Janine
  • Janine needs café equipment layout in CAD within ~2 weeks for DD phase — Jack (L1 kitchen specialist) to provide
  • Corner unit MEP revisions: Nolan sent updated layouts Apr 29 — Roby needs to review and pick 1 Bed Type 3 layout
Operations Cabinets in Kalona Apr 22, 2026 · 2:00 PM
Roby
  • Cabinet sourcing / site visit in Kalona — VE option for residential unit cabinets/casework
Construction Owner-Provided Items Review Apr 22, 2026 · 8:55 AM
Roby
  • Rediframe hidden mechanical door — fire-rated
  • Reviewed scope of owner-provided items to separate from Andy's GC scope